IRELAND
Ireland’s prevailing south-westerly winds from the
Atlantic Ocean give a feasible wind resource that
has been estimated to be as high as 179 GW, or some
40 times the country’s current generating capacity.
However, the accessible resource is about 2 190 MW
and, in reality, the practicable resource is estimated
to be 812 MW.
This abundant wind supply began to be utilised, albeit
rather poorly, in the early 1980’s with several demonstration
schemes. The detailed investigations that followed
included the establishment of the Irish Wind Atlas
and, in the mid-1990’s, the Government’s Alternative
Energy Requirement (AER I) competition. Under AER
I, prospective generators competed for Power Purchase
Agreements (PPA’s) to sell electricity to the Electricity
Supply Board (ESB). The competition was open to a
range of renewable energies for contracts of 10-15
years’ duration, not extending beyond 2010 (all projects
were to completed near end-1997). Wind energy gained
ten contracts for 73 MW: seven were eventually built.
The second competition (AER II) excluded wind energy
but AER III, launched in March 1997, included a target
of 90 MW for new wind energy projects. The results,
announced in April 1998, granted PPA’s to 17 projects
with a combined capacity of 137 MW, to be located
in Counties Cork, Donegal, Kerry, Roscommon and Sligo.
The PPA’s were for 15 years’ duration, not extending
beyond 2014.
A Government green paper on sustainable energy released
in September 1999 not only reiterated Ireland’s determination
to promote renewable energies and, in particular,
the utilisation of wind power, but also dramatically
increased the target figures for the period to 2005.
It is now expected that wind energy will contribute
the bulk of 500 MWe of additional generating capacity
(replacing an earlier target of 155 MWe). If this
target is met, wind energy will then account for 10.7%
of projected total installed electricity generating
capacity.
The first commercial wind plant at (Bellacorick, County
Mayo) was commissioned in 1992. The 21 turbines have
a combined capacity of 6.45 MW. It remained the only
windfarm supplying the grid until 1997, when a further
six were commissioned (under AER I and the EU’s Thermie
Programme), with a combined generating capacity of
44 MW. Since then a further five have been constructed,
including the 4.62 MW Curabwee plant in County Cork,
the first under AER III. By mid-2000, the 12 operating
Irish windfarms had a combined capacity of 69 MW,
representing 1.4% of total installed electricity generating
capacity.
Of the 17 projects awarded under AER III (excluding
the Curabwee plant) nine have secured planning, three
have failed at the planning stage and the remaining
four are at various stages of the planning process.
It was expected that the eight stations under construction
in 2000 would bring the end-2000 total installed capacity
to 117 MW.
COUNTRY NOTES
(WIND ENERGY)
Argentina
|| Canada
|| China
|| Denmark
|| Germany
|| Greece
|| India
|| Ireland
|| Italy
|| Japan
|| Netherlands
|| Spain
|| Sweden
|| United Kingdom
|| United
States Of America